August 12, 2010
Present:
David Willey, Dennis Westlind, Sandi Thorson, Pastor Jim, Intern Pastor Chris,
Tanya & Byron Hensch, Stuart Fleischauer, Betty Johansen, Connie Hanyzewski, Jon
Hartman, Le Boyer, Amy Drake, Karen Frederick, Vern & Muriel Foster, Gary
Johnson, Susan Thompson, Lowell Wilcox, Karen Zell. Recording person: Lynn
Melchior
The
meeting began at 6:30 p.m. The meeting was split into three parts: Guest
speaker Mike Henkenius, a presentation from Gary Johnson on Mission Builders and
a “where do we go from here” wrap up session.
Mike Henkenius:
Mike was involved in Our Lady of The Lake Catholic Church’s construction project
in Battle Lake. After 5 years of planning, they broke ground in April 2008 and
completed construction in July 2009. They added 11,500 sq ft of sanctuary
(seating 750), offices, library and restrooms. In the planning stages, they:
1)
Wrote a “needs assessment”. Although the building
met the basic needs it did not meet summer, wedding, funeral, etc needs. They
also reviewed demographics.
2)
Wrote a “requirements statement”.
3)
Hired Davies & Associates out of St. Cloud to be
their capital fundraisers. Davies determined what could be raised in a 3 year
campaign. The building was paid for by monies already in the bank, a capital
fundraiser and a loan from the archdiocese. Their budget was $1.7 million and
it actually cost $1.9 million. Davies were paid a flat fee up front.
4)
Interviewed builders. Initially they hired Roers
Construction out of Fargo. However, their design was beyond their budget due to
a tie-in with the existing building on the hill. Their second choice was Curtis
Construction. Curtis built First Lutheran in Battle Lake. Curtis’ design was
different in how it added onto the existing church. However the estimate was
based on First Lutheran’s experience – and inflation, cost of diesel, building
supplies, etc went up since the First Lutheran project. Plus the cost of the
remodel of the existing church was more expensive than expected due to hidden
costs. Mike felt that a year was lost working with Roers.
Issues
Our Lady of the Lake experienced in building:
§
They did
not hammer out the contract enough due to timing issues.
§
They did
not have a clear understanding of contract changes.
§
They had
subcontractor disputes due to not understanding subcontractor contracts.
§
They
needed one contact with Curtis (instead they had a committee which became
confusing).
What
they learned:
§
Get
expectations met upfront. Curtis Construction changed ownership during the
project and the expectations changed.
§
Good
documentation is a must.
§
Lower the
ceiling, lower the cost, i.e. sanctuary space is more expensive to build.
§
New site
was cheaper than dealing with an existing building.
§
Remodeling was cheaper when done in house. Mike cited the construction of their
new kitchen as an example. The new kitchen was taken out of the contract and
finished with volunteers after the building project was completed and as money
was available.
Gary Johnson & Mission Builders:
After
working as an engineer whose firm started the design build process in MN, Gary
owned his own Mechanical Engineering firm. He retired early to spend time in
the Peace Core and then worked with Mission Builders as a construction manager
and later managed all of Mission Builders for the ELCA. Mission Builders is a
volunteer ELCA organization that assists in the construction of churches across
the United States. Mission Builders was started in the Missouri Synod as
“Laborers for Christ”. Now “Laborers for Christ” mostly choose construction
projects that include schools. Gary believes communication is key when working
with builders – and even with great communication, no one gets it right. There
will always be issues.
Gary said
there are 4 ways to go about construction:
1)
Hire an architect, have the architect gather
estimates and hire a builder.
2)
Hire a contractor who put the estimates together
with a price guaranteed based on criteria.
3)
Mission Builders. Volunteers are paid minimum wage
so they are covered by worker’s comp. They work Tues thru Sat and live in RVs
in the parking lot. The congregation provides volunteers to help in
construction, lunches and breaks 2x a day. This can be good for the church as it
brings people together. Mission Builders hire out insulation, sheet rock and
concrete work. There is no wait for Mission Builders right now.
4)
Do it yourself - appointing one person as
construction manager.
Number 1
is the most expensive while #4 is the least expensive. Gary emphasized that
criteria is important. Once you have criteria, get contractors to give you bids
and develop a budget. The ELCA does have a Mission Investment Fund that helps
with how to finance projects. It does not do fundraising but is a great first
step. Gary thought the questions of “what do we need” and “what can we afford”
are a two pronged effort and can be done simultaneously.
Wrap-up:
Dave W.
indicated that we are now at the time to start talking to contractors and
getting estimates. Dick H. has offered to do the initial architectural drawings
as a starting place. This allows us to start gathering information regarding
costs. This then allows us to start getting congregational support. A question
was raised: the congregation has the capability but does it have the energy? A
question was also raised as to if we really need the addition or should we be
raising money for other church’s building programs or mission needs. It was
suggested that part of the capital fundraising (i.e. 10%) be donated to
something like Humble Walk’s building needs. A discussion followed regarding
needs vs wants at Zion.
The next
step is for each group to meet with Dick H. and discuss criteria for their
areas. Currently there are two approaches:
1.
Four Pod Approach. This entails building out in
four separate areas in the existing building.
2.
One Wing Approach. This entails building one
larger wing out to the South for all needs.
A third
alternative of building out north or a whole new building were briefly
discussed.
Dave also
indicated that we need to be prepared to accept ideas from the outside.
The
meeting was adjourned at 7:45 p.m. The next BPC meeting will be Thursday,
August 19th at 6:30 p.m.

July 29, 2010
Present:
David Willey, Dennis Westlind, Chuck Erickson, Sandi Thorson, Pastor Jim, Tanya
& Byron Hensch, Stuart Fleischauer, Keith Fleischauer, Casey Haack, Betty
Johansen, Connie Hanyzewski, Jon Hartman, Le Boyer, Amy Drake, Chris Maudal,
Karen Frederick, Vern & Muriel Foster, Gary Harrington. Recording person:
Connie Hanyzewski
The
meeting began at 6:30 p.m. David Willey wanted to hear from the various areas
as to where they thought they were in their process.
INFRASTRUCTURE:
Dennis W. discussed the energy audit that will be done on the current building.
He reiterated the fact that this audit will be done at no out- of-pocket cost to
Zion. Stan Simon can do the audit sometime in August; however, certain
information needs to be obtained and provided to Stan prior to him coming.
Items needed:
1)
As much data as possible on the current structure –
“as built drawings” would be helpful. We have some drawings already but someone
needs to go through them and put them in order showing our current structure.
Dennis will look at forming a sub-committee to get the job done.
2)
We need the energy costs from the last 2 – 3
years. The office will provide this information.
Refer to
the notes of July 20th for the detailed reasons why we are
doing this energy audit. Basically, we need to do an audit on the existing
facility to assess energy efficiency for current and future building needs.
Discussion occurred regarding types of “green” energy such as solar, geothermal,
etc. Glendalough has a new office building with solar heat that might be a good
idea to check out.
EDUCATION:
Tanya H.
reviewed the space requirements and multi usage for Sunday school rooms,
Confirmation, Adult Ed, Library, Activity room, quilting, etc. We discussed how
all of this new space could serve as overflow for Fellowship Hall, as needed.
Tanya sent current square footage of space to Lynn M.
WORSHIP:
Sandi T.
reviewed the option of having a room behind the front Sanctuary that would house
choir robes, music files, all sacristy items, which includes communion trays,
wine, etc., and the sanctuary banners, paraments, and candles. It was mentioned
we should visit some other churches to see the space requirements for all these
items so approximate square footage could be obtained.
Chris M.
brought up the issue of space for the choir and contemporary musicians. Was
there any way, the Sanctuary could be enlarged to provide more space for these
folks in the worship area? A discussion followed the question. David W. said
it was good it was brought up.
Stuart F
& Jon H. brought up the idea of using the current sacristy space. By enlarging
it and going east to match up with the building, it would provide a room for
parents with small children that need to leave the sanctuary periodically. A
window and speaker could be installed.
ADMINISTRATION:
Gary H. asked how much information was needed prior to talking
to a builder or architect. Admin has the proposed square footage and details of
what they need for office/meeting space. Is that enough? Should we leave it up
to the builder to provide the best use of space?
We
started this process identifying the function(s) required, we attached
attributes and then we figured what we would like to have. Have we done that?
We might
need to bring in a builder or architect to pull everything together. At what
point do we say we are ready for the next step. David W. said we need an
“architectural rendering” for the congregation. The rendering would provide
something visible with an estimate of cost.
Keith F.
suggested we bring in members from other area churches that have had additions
put on or have built to get an idea if we are at a point to bring in a
professional. Keith F., Stuart F., and Gary H. will invite a representative
from Eagle Lake, First Lutheran, and Our Lady of the Lake to our next meeting.
In
addition, to a Q & A, we will ask them to provide us with the following:
1)
What ended up being really good about what they
did.
2)
What would they have done differently if they could
do it all over again?
3)
How did they know they were ready for the
professionals to come and be a part of the project?
4)
Are we at that point?
5)
How did they handle the funding of their building
projects?
The
meeting was adjourned at 7:50 p.m. The next BPC meeting will be Thursday,
August 12th at 6:30 p.m.

July 20
Present: Dave Willey, Chuck
Erickson, Richard Hagemeister, Sandi Thorson, Pastor Jim, Dick Gyllstrom, Tanya
and Byron Hensch, Stuart Fleischauer, Connie Hanyzewski and Jon Hartman.
Recording Secretary: Lynn Melchior.
The meeting began at 5:58
pm. Dave Willey commented that the BPC members have adopted an sense of
pragmatism. This fits well with our congregation. Dave also discussed the good
thinking of multi-use space where functionality of several areas can be met with
one room. As Zion’s space needs are coming together, the BPC can begin moving
towards solutions for the space needs.
Each subgroup then reported
their status:
EDUCATION:
Tanya H reviewed the Ed subgroups last meeting which focused on multi-use rooms,
utilizing existing areas and the possibility of not needed a dedicated 7th
and 8th grade room. This age group may be better suited using
different areas of the church as needed by their lesson plans. Please see BPC
ED 7-19-10 minutes for more information.
The possibility of having
weekday daycare at Zion was discussed. Experiences of other church day cares
were expressed; location was discussed (SS rooms) and the fact that this is not
necessarily a money maker for Zion but an outreach possibility. Zion’s location
may be too remote from people’s work and hospitals to be comfortable for some
parents.
A Nursery was discussed.
Where should this room be located? Could it be multi-used with Prek/Kdg/Mops?
The Nursery will need to meet all applicable codes (which can be tough) and have
speaker/video system installed in order to hear/see the service.
Adult Education/Family Room
was discussed. This is thought to be a large room that can hold a minimum of 50
people. It could be used as a fellowship overflow. However, it was also
discussed that if this is also used as a family room for weddings, funerals, etc
then perhaps it should be more near the administration and Narthex areas.
ADMINISTRATION:
Dick G reviewed their interim report. Note: This report basically covers a
summary of Sq. Ft. estimates with some specific pertinent comments. Final
report to follow.
1.
Pastors Office
-
Space needs 256 Sq. Ft. minimum/current space is 188 Sq. Ft.
-
Office space to include small conference area with small table and 3 – 4 chairs
-
Consideration of dual entry with access to small conference room
-
Other details included in June 29th meeting with Pastor Jim, Pat and
Connie
2.
Intern Pastor Office
-
Space needs 100 Sq. Ft minimum/current space is 65 Sq. Ft. usable
-
Location in close proximity to Pastor’s Office
3.
Future Pastor Office (time frame not determined)/ Interim storage/usable space
-
Space needs 200 Sq. Ft.
-
Location in close proximity to Pastor’s Office
4.
Church Office & Administrative
-
Space needs 480 Sq. Ft./current space is 249 Sq. Ft.
-
Separate adjoining area for office equipment and supplies
-
Includes reception area
-
Easy access to small conference room
-
Other details included in June 29th meeting with Pastor Jim, Pat and
Connie
5.
Parish Nurse and Volunteer Coordinator
-
Space needs 144 Sq. Ft.
6. Small
Conference Room
-
Space needs 320 Sq. Ft.
-
Includes 80 Sq. Ft. of storage space
Current total Sq. Ft.
502
Proposed total Sq. Ft.
1500
Notes: 1. Offices
1,2,3 and 5 require “internal” viewing window.
2. During
the course of the study the group noted the opportunity
and
need for additional Fellowship Hall space.
WORSHIP:
Sandi T. reported that the
worship groups main need was an Apse. This could easily be created by putting
an addition on to the existing sanctuary to the North. No changes would be made
to the existing sanctuary walls. The Apse would allow for music needs, music
storage and the sacristy. It would have an access to the parking lot as well.
INFRASTRUCTURE:
Chuck E. reviewed his findings on obtaining and energy audit for Zion. He
reports the energy audit costs which are between $2,500 and $4,500 will be
picked up by Lake Region and Great River Energy. Chuck received permission to
get started on the energy audit. The infrastructure subgroup’s meeting notes
are as follows:
Scope:
Building Issues
Sub-committee is tasked to identify, investigate/analyze, document and recommend
an approach to areas within the Zion church’s property, structural & land, that
require decisions generic to a new, existing, remodel or add-on structure.
The sub-committee will state
issues as well as identify opportunities that provide cost effective approaches
to building, maintaining, energy savings and future needs of the congregation.
Items of Coverage:
Areas identified to date
that require investigation include the following. This is to be a living
document as the project progresses.
HEATING & COOLING
-
Cost analysis &
facility analysis of existing structure over the last 5 years. Heat vs
cooling/other.
-
Perform thermal
analysis of existing structure
-
Make
recommendations of energy upgrade to lower yearly costs by 25% by 2012
-
Develop plan on
cost effective ways to heat & cool
○
Sanctuary
○
Narthex
○
Offices
○ Sunday School Rooms
○ Kitchen/Fellowship Hall
-
Insulation
upgrades needed
-
Suggestion as to
enclosed areas with doors vs openness
-
Programmable
thermostat/facility usage/peak load
-
Suggesting to
architect as to ceiling 8’, 9’, 10’, vault, etc. (room volume)
-
Geothermal
investigation and plan
HOT WATER SYSTEM
○ Centralized vs location/demand
○ Off peak
○ Type of heaters
WELL
○ Size of existing well (capacity)
○ Future needs
- God’s Acres or other
- Expansion of facility
SEWER OPTIONS
○ Additional location
○ Leave as is
○ Modify existing system
RE-SHINGLE
○ Upgrade insulation (R-Value)
○ Wafer Board concept
○ Redesign of ceiling (internal)
WINDOW SELECTION ON NEW AREAS & REMODEL/EXISTING
SIDING SELECTION ON NEW AREAS & REMODEL/EXISTING
OLD DRAWINGS
○ Review “old” drawings for pertinent data
○ Existing R Value
○ Structural designs
ELECTRICAL COVERAGE
○
Present size
○ Increase amperage anticipated
○ Major load change, off peak, etc.
PARKING LOT MASTER PLAN
○
Where (design plan)
○
When
○
Fill
○ Coverage
○ Etc.
SUNDAY SCHOOL ROOM (existing)
○ Roof removal & replacement plan
SITE PLAN
○ Develop master drawing
(scale) of existing structure, set backs, well, sewer, power poles, transformer,
parking lot, entrances, etc.
PRIORITIES:
On going meetings have
resulted in prioritizing the list, in that energy cost control is top
priority, e.g. heating & cooling and/or associated insulation (or lack of) must
be addressed.
As building plans go forward, new additions must address latest
energy savings but existing structure must be looked as an opportunity to bring
them up to speed. As an example, outside wall of the fellowship area (west
side) should be upgraded to Hi-R value. Options may be to go from a 2 x 4 thick
wall to a 6” wall with Hi-R such as foam and possible new windows.
To get a handle on existing structure heat loss, a thermal
analysis is suggested for all areas of the buildings. This is probably going to
be a cost item to the congregation unless a cost share is offered.
Heating and cooling and all the options are being addressed as a
priority. With all the different build phases over the years, what is the right
answer for total control of our energy costs? Is it to go total Geothermal for
heating/cooling energy source, keeping some existing systems, modularize new
system, etc.
Priorities are being established to ensure that near term
projects must be coordinated so as nothing has to be redone during the new
building process.
PRESENT STATUS:
To date presentations have been made by LREC on Geothermal and
opportunities for horizontal boring as to cost benefits along with a lease vs
buy option.
Barry Excavation has discussed present sewer and possible future
county/state waste disposal requirements.
ON GOING DEVELOPMENT:
To implement a priority item of thermal analysis of existing
structure, LREC has been contacted. They have stated an effort will be
performed for Zion but anticipated a cost between $2500 to $4500. However, they
have now offered that Great River Energy will pay for half the cost & LREC will
pay for the other half. Therefore, no cost to Zion Lutheran Church. The energy
audit will be performed by a mechanical engineer from Kerkhoven, MN once be can
be scheduled. Chuck Erickson will coordinate the effort.
The site master plan is ongoing as to existing
structure, well, sewer, power pole, etc.
Parking lot master plan is being developed.
“Old” drawings are under review.
The meeting was adjourned
at 7:07 pm. The next BPC meeting will be Thursday,
July 29th at 6:30 pm.

July 19, 2010
Present: Tanya Hensch, Muriel Foster, Karen Zell, Dave Willey, and Lowell
Wilcox. Recording Secretary: Lynn Melchior.
The
meeting started at 6 pm.
The
subgroup discussed the advisability of having as many rooms as possible being
cross utilized. For example, could the adult ed room or the SS common room be
used also for fellowship expansion and overflow? Multi-use rooms are good
selling points.
The
subgroup also discussed the assets we currently have in courtyards and
landscaping – and how to incorporate those in current planning. The possibility
of removing the fireplace (which is non functional) and replacing the space with
doors and windows to utilize outside fellowship was discussed.
To
better understand possible expansion space, the group walked around the outside
of the church exploring possible areas of expansion for the Education needs.
Dave Willey was able to point out several options.
The
remainder of the meeting was spent discussing room requirements for education.
The rooms discussed were: Adult Ed, SS Common, PreK/Kdg/Mops, 1st –
2nd grades, 3rd – 4th grades, 5th –
6th grades, 7th and 8th grades,
storage/utilities, restrooms, Youth and Library.
The
notes for each room requirement will be updated and emailed to each BPC:
Education group member.
The
meeting adjourned at 7:43 pm.

July 8, 2010
Present: Dennis
Westlind, Keith Fleischauer, Le Boyer, Dave Willey, Chris Maudal, Chuck
Erickson, Richard Hagemeister, Lowell Wilcox, Sandi Thorson, Gary Harrington,
Betty Johansen, Karen Frederickson, Pastor Jim, Dick Gyllstrom, Marilyn Wahlgren
and Laremie Barry. Recording Secretary: Lynn Melchior.
The meeting began
at 6:31 pm. Dave Willey began the meeting talking about the next steps for the
BPC. See Handout “Building Committee Interim Report Outline”. Thru the various
subgroups, the BPC is looking to consolidate the data in a more concise format;
to create a document that is a statement of needs just short of a floor plan.
This will help determine the specific building/floor plans needed. Several
questions still need to be answered:
-
What programs
and services will Zion offer in the future? How will this affect the
proposed building?
-
What does Zion
predict for membership growth?
-
How do we meet
our parking needs – currently and in the future?
Dave suggested that
we set aside the idea of a new sanctuary and think thru options with the
existing facility and extending the existing facility. For example, if the roof
line was extended to the south in the current administration area to the setback
line, the added space would be 1,620 sq ft. How could that new space be used and
how could the old admin space be used? It is in exploring the reasonable options
that meet the major needs that will help in exploring additional options (like
new worship space). If we determine that a new sanctuary is needed, then how
best to handle the old space will be discussed.
Additional
expansion space estimates are: Expand admin and library to the south and 2,304
sq ft is added. Once the education second floor is removed, 320 sq ft is
available. Further expansion North and West of the current Sunday School space
allows for even more expansion space. NOTE: Removal of the 2nd floor
of the Sunday School wing constitutes a 1,800 sq ft space loss that will have to
be made up somewhere else.
Secure storage
(fire proof) was discussed and assigned to the Admin subgroup. It was also
noted, that people need quick access to the admin area, so that must kept in
mind when planning the Admin area. Prioritization of needs, common space, user
communities, and double door entries were also discussed. The Infrastructure
subgroup will focus on how current facilities are working, how they will work
with the proposed building and what Zion needs to move toward.
ACTION ITEMS:
-
A current site
plan is needed. Dennis Westlind and Dick Hagemeister will create a drawing
that will show current facilities, setbacks, well, septic, etc. A box of
drawings in the large Sunday School Room may help with this.
-
Subgroups need
to be more formalized. Lynn will send out a subgroup listing.
-
A form will be
created to help the subgroup formalize their respective needs.
There is a conflict
with BPC meeting times for the next two weeks. It was determined that each
subgroup will need to meet individually next week to work on their needs forms.
The following week, the BPC as a whole will meet on Tuesday July 20th
at 6:00 pm.

July 1, 2010
MAIN
MEETING: Present:
Amy Drake, Dennis Westlind, Keith Fleischauer, Le Boyer, Dave Willey,
Muriel and Vern Foster, Gary Johnson, Tanya and Byron Hensch, Chuck Erickson,
Richard Hagemeister, Lowell Wilcox, Sandi Thorson, Pat Garza, Gary Harrington,
Casey Haack, Betty Johansen, Karen Frederickson, Pastor Jim, Intern Pastor
Chris, Diane Weeks, Connie Hanyzewski, Dick Gyllstrom and Laremie Barry.
Recording Secretary: Lynn Melchior.
The
meeting began at 6:25 pm. The first order of business was a presentation by Dan,
Energy Services Director at Lake Region Power on Geothermal technology and how
it might benefit Zion. The Geothermal technology can be used for heating and
cooling. It uses the renewable energy from the earth to heat and cool.
Lake
Region is offering a new program where they own, install and maintain the closed
loop system and a fixed monthly charge is added to your electric bill. (The
building owner must still pay for the heat pump and duct work.) This monthly
charge is fixed for 35 years. It effectively locks in your heating and cooling
charges, which are 70% of your energy consumption. Occasionally a secondary
heating source may be needed. The remaining 30% of the energy charges is lights,
appliances, etc. This is primarily a residential process – commercial buildings
need customized installations and charges. The closed loop system can be
purchased at a depreciated price. Current prices for a horizontal bore are
$1,700 and $1,800 to $2,100 vertical. Well locations are depicted in the
easement with GPS locations.
Lake
Region utilizes horizontal drilling at a depth of 15 ft for 200 – 250 ft in
length. The soil type, loads needed and distance between pipes must be known
for geothermal sizing. Vertical drilling can also be used in Geothermal
technology but then a well driller must be involved as anything deeper than 25
feet requires a well drilling permit. The pipes are filled with methanol.
Backfill is used to maximize energy conduction. Easements may need to be
recorded and setbacks observed on smaller lots. Test bores may also be needed
for larger projects. An existing structure should have an energy audit.
A video
showed horizontal drilling and talked about the merits of geothermal. Dan also
provided a handout that covers the new geothermal program at Lake Region.
The
second order of business was to create a new sub group of the BPC. It will
focus on worship and fellowship. Current members are Sandi, Amy, Pastor Jim and
hopefully, Chris Maudal.
Two
additional handouts were also provided: Betty Johansen of the library committee
passed out the long range planning request for the Zion Library. Dave Willey
passed out ELCA suggestions for church sizing.
INFRASTRUCTURE SUB-GROUP:
Immediately after LREC presentation, the infrastructure sub-group discussed
“sewer” with Laramie Barry. Attendees were Chuck Erickson, Keith Fleischauer,
Dick Hagemeister, Dennis Westlind, Stuart Fleischauer, Pastor Jim, Le Boyer and
Gary Johnson & Lowell Wilcox. Recording Secretary: Dennis Westlind.
Items
discussed:
● Present
drain field at north of kitchen is approximately 3 feet by 25 feet with a
“small” tank.
● Appears that kitchen
and sanctuary bathrooms are “Y’d” towards small tank.
● Present field has
not been disturbed except for adding cleanout Y and
additional pipe for
future heat tape (or steam). Work done because of “deepfreeze”.
● We probably don’t
need to update existing field but church expansion may dictate another field or
change existing field (it is building design dependent). May need lift pump.
● We are presently at
approximately 600 members.
● 25 to 30 Sunday
School attendees
● Dishwasher will
require 50% bigger tank on new system (County/State rule).
● As a “swag” our new
plan may require a tank(s) and leach field similar to a 4 bedroom house (may go
to that of 5 bedroom house equivalent).
ADMINISTRATION:
The administration
sub-Group met on June 29th. The following is the minutes from that
meeting.
Zion
Bldg/Planning Committee
Meeting with Pastor Jim, Pat G. and Connie June 29, 2010
From:
Dick Gyllstrom and Diane Weeks
Subj.: Pastor/Office Administrative Offices
The
purpose of the meeting was to explore office requirements and needs. The
primary goal was to discuss the variety of musts, needs and wants typically
found in the Pastor/Office Staff office complex.
Pastors Office
-
Space for
small counseling area, 3 to 4 chairs with small table for personal counseling
(family, marriage, etc.)
-
Possible
dual entry
-
Have Senior
Pastor/Assoc. Pastor/Intern office proximity
-
Easy access
to separate staff/general purpose meeting room
-
Personal
Library Space (basically bookshelves)
-
Closed
Cabinets (Lockable)
-
Lockable AV
equipment storage unless located in general office area
Note: Some measurements were taken of Pastor’s existing office to determine if
present size would be adequate. Determined that the 256 Sq Ft noted in the June
24th group meetng notes would be adequate and needed. Other area
sizes noted in those notes will likely need to be further evaluarted as we go.
Church Office and Associated Space
-
Recommend
open area with controlled access/ counter between office space and visitors.
-
Need space
for coats/personal items
-
Upgrade
phone system/more flexibility
-
Lockable
space for Audio/Visual
-
Copy
Area/need functional, controlled space
-
Security
Vault
-
Need
detailed review of PC use and needs
-
Use close
proximity conference/meeting room for organizing mass mailings
Note: There were other office/productivity/work related ideas that should be
considered that do not necessarily affect square footage requirements.
Further detailed discussion will be needed as space layouts and other options
are considered.
The
BPC will meet weekly on Thursday evenings at 6:30 pm. The next meeting is July
8th. Thoughts and comments can be emailed to Dave Willey in between meetings.

June 24, 2010
Present:
Stuart Fleischauer, Amy Drake, Dennis Westlind, Keith Fleischauer, Le
Boyer, Dave Willey, Muriel and Vern Foster, Gary Johnson,
Tanya Hensch, Chuck Erickson, Susan Thompson, Richard
Hagemeister, Lowell Wilcox, Sandi Thorson, Pat Garza, Gary Harrington.
This BPC
meeting was divided into 3 basic areas to investigate, start qualifying and
documenting requirements. The areas discussed were administration, education
and infrastructure. The three groups met separately for 45 minutes to define
these needs.
ADMINISTRATION:
Participants were: Sandi Thorson, Pastor Jim, Vern Foster, Pat
Garza, Susan Thompson, Gary Johnson, and Gary Harrington, who facilitated. Pat
Garza was the Administration meeting recorder.
Administration square footage proposed.
Pastor’s
office—256 sq ft
Intern
office—86 sq ft
Secretary—360 sq ft
Parish
nurse—190 sq ft
Future
associate Pastor—200 sq ft
Conference/meeting room—480 sq ft