Home
Calendar
Announcements
Council Corner
Foundation
Get Involved
Learn With Us
Library
New Members
Photo Gallery
Sermon
Visit Us
Worship With Us
Youth
Zion History
Zion Staff

VARIOUS LINKS

ELCA Daily Bible Reading

Luther Crest

Lutheran Social Services

Lutheran Woman Today

Northwestern MN Synod

 

Weather Related Announcements

Click above for the area forecast

 

Planning/Building Committee Minutes

August 12, 2010 

Present:  David Willey, Dennis Westlind, Sandi Thorson, Pastor Jim, Intern Pastor Chris, Tanya & Byron Hensch, Stuart Fleischauer, Betty Johansen, Connie Hanyzewski, Jon Hartman, Le Boyer, Amy Drake, Karen Frederick, Vern & Muriel Foster, Gary Johnson, Susan Thompson, Lowell Wilcox, Karen Zell.  Recording person:  Lynn Melchior 

The meeting began at 6:30 p.m.  The meeting was split into three parts: Guest speaker Mike Henkenius, a presentation from Gary Johnson on Mission Builders and a “where do we go from here” wrap up session.

Mike Henkenius:  Mike was involved in Our Lady of The Lake Catholic Church’s construction project in Battle Lake.  After 5 years of planning, they broke ground in April 2008 and completed construction in July 2009.  They added 11,500 sq ft of sanctuary (seating 750), offices, library and restrooms.  In the planning stages, they:

1)    Wrote a “needs assessment”.  Although the building met the basic needs it did not meet summer, wedding, funeral, etc needs. They also reviewed demographics. 

2)    Wrote a “requirements statement”. 

3)    Hired Davies & Associates out of St. Cloud to be their capital fundraisers.  Davies determined what could be raised in a 3 year campaign.  The building was paid for by monies already in the bank, a capital fundraiser and a loan from the archdiocese.  Their budget was $1.7 million and it actually cost $1.9 million.  Davies were paid a flat fee up front.

4)    Interviewed builders.  Initially they hired Roers Construction out of Fargo.  However, their design was beyond their budget due to a tie-in with the existing building on the hill.  Their second choice was Curtis Construction.  Curtis built First Lutheran in Battle Lake.  Curtis’ design was different in how it added onto the existing church.  However the estimate was based on First Lutheran’s experience – and inflation, cost of diesel, building supplies, etc went up since the First Lutheran project.  Plus the cost of the remodel of the existing church was more expensive than expected due to hidden costs.  Mike felt that a year was lost working with Roers. 

 Issues Our Lady of the Lake experienced in building:

§         They did not hammer out the contract enough due to timing issues.

§         They did not have a clear understanding of contract changes.

§         They had subcontractor disputes due to not understanding subcontractor contracts.

§         They needed one contact with Curtis (instead they had a committee which became confusing).

 What they learned:

§         Get expectations met upfront. Curtis Construction changed ownership during the project and the expectations changed.

§         Good documentation is a must.

§         Lower the ceiling, lower the cost, i.e. sanctuary space is more expensive to build.

§         New site was cheaper than dealing with an existing building.

§         Remodeling was cheaper when done in house.  Mike cited the construction of their new kitchen as an example.  The new kitchen was taken out of the contract and finished with volunteers after the building project was completed and as money was available.   

Gary Johnson & Mission Builders:  After working as an engineer whose firm started the design build process in MN, Gary owned his own Mechanical Engineering firm.  He retired early to spend time in the Peace Core and then worked with Mission Builders as a construction manager and later managed all of Mission Builders for the ELCA.  Mission Builders is a volunteer ELCA organization that assists in the construction of churches across the United States.  Mission Builders was started in the Missouri Synod as “Laborers for Christ”.  Now “Laborers for Christ” mostly choose construction projects that include schools.  Gary believes communication is key when working with builders – and even with great communication, no one gets it right.  There will always be issues. 

Gary said there are 4 ways to go about construction:

1)    Hire an architect, have the architect gather estimates and hire a builder.

2)    Hire a contractor who put the estimates together with a price guaranteed based on criteria.

3)    Mission Builders.  Volunteers are paid minimum wage so they are covered by worker’s comp.  They work Tues thru Sat and live in RVs in the parking lot.  The congregation provides volunteers to help in construction, lunches and breaks 2x a day. This can be good for the church as it brings people together.  Mission Builders hire out insulation, sheet rock and concrete work.  There is no wait for Mission Builders right now.

4)    Do it yourself - appointing one person as construction manager.   

Number 1 is the most expensive while #4 is the least expensive.  Gary emphasized that criteria is important.  Once you have criteria, get contractors to give you bids and develop a budget.  The ELCA does have a Mission Investment Fund that helps with how to finance projects.  It does not do fundraising but is a great first step.  Gary thought the questions of “what do we need” and “what can we afford” are a two pronged effort and can be done simultaneously.   

Wrap-up:  Dave W. indicated that we are now at the time to start talking to contractors and getting estimates.  Dick H. has offered to do the initial architectural drawings as a starting place.  This allows us to start gathering information regarding costs. This then allows us to start getting congregational support.  A question was raised: the congregation has the capability but does it have the energy?  A question was also raised as to if we really need the addition or should we be raising money for other church’s building programs or mission needs.  It was suggested that part of the capital fundraising (i.e. 10%) be donated to something like Humble Walk’s building needs.  A discussion followed regarding needs vs wants at Zion.   

The next step is for each group to meet with Dick H. and discuss criteria for their areas.  Currently there are two approaches:

1.     Four Pod Approach.  This entails building out in four separate areas in the existing building.

2.    One Wing Approach.  This entails building one larger wing out to the South for all needs.

A third alternative of building out north or a whole new building were briefly discussed.    

Dave also indicated that we need to be prepared to accept ideas from the outside. 

The meeting was adjourned at 7:45 p.m.  The next BPC meeting will be Thursday, August 19th at 6:30 p.m.   

July 29, 2010 

Present:  David Willey, Dennis Westlind, Chuck Erickson, Sandi Thorson, Pastor Jim, Tanya & Byron Hensch, Stuart Fleischauer, Keith Fleischauer, Casey Haack, Betty Johansen, Connie Hanyzewski, Jon Hartman, Le Boyer, Amy Drake, Chris Maudal, Karen Frederick, Vern & Muriel Foster, Gary Harrington.  Recording person:  Connie Hanyzewski

The meeting began at 6:30 p.m.  David Willey wanted to hear from the various areas as to where they thought they were in their process. 

INFRASTRUCTURE:  Dennis W. discussed the energy audit that will be done on the current building.  He reiterated the fact that this audit will be done at no out- of-pocket cost to Zion.  Stan Simon can do the audit sometime in August; however, certain information needs to be obtained and provided to Stan prior to him coming. 

         Items needed:

        1)    As much data as possible on the current structure – “as built drawings” would be helpful.  We have some drawings already but someone needs to go through them and put them in order showing our current structure.  Dennis will look at forming a sub-committee to get the job done.   

2)    We need the energy costs from the last 2 – 3 years.  The office will provide this information.

Refer to the notes of July 20th for the detailed reasons why we are doing this energy audit.  Basically, we need to do an audit on the existing facility to assess energy efficiency for current and future building needs.

Discussion occurred regarding types of “green” energy such as solar, geothermal, etc.  Glendalough has a new office building with solar heat that might be a good idea to check out.

EDUCATION:  Tanya H. reviewed the space requirements and multi usage for Sunday school rooms, Confirmation, Adult Ed, Library, Activity room, quilting, etc.  We discussed how all of this new space could serve as overflow for Fellowship Hall, as needed.  Tanya sent current square footage of space to Lynn M.

WORSHIP:  Sandi T. reviewed the option of having a room behind the front Sanctuary that would house choir robes, music files, all sacristy items, which includes communion trays, wine, etc., and the sanctuary banners, paraments, and candles.  It was mentioned we should visit some other churches to see the space requirements for all these items so approximate square footage could be obtained. 

Chris M. brought up the issue of space for the choir and contemporary musicians.  Was there any way, the Sanctuary could be enlarged to provide more space for these folks in the worship area?  A discussion followed the question.  David W. said it was good it was brought up. 

Stuart F & Jon H. brought up the idea of using the current sacristy space.  By enlarging it and going east to match up with the building, it would provide a room for parents with small children that need to leave the sanctuary periodically.  A window and speaker could be installed.  

ADMINISTRATION:  Gary H. asked how much information was needed prior to talking to a builder or architect.  Admin has the proposed square footage and details of what they need for office/meeting space.  Is that enough?  Should we leave it up to the builder to provide the best use of space? 

We started this process identifying the function(s) required, we attached attributes and then we figured what we would like to have.  Have we done that? 

We might need to bring in a builder or architect to pull everything together.  At what point do we say we are ready for the next step.  David W. said we need an “architectural rendering” for the congregation.  The rendering would provide something visible with an estimate of cost. 

Keith F. suggested we bring in members from other area churches that have had additions put on or have built to get an idea if we are at a point to bring in a professional.  Keith F., Stuart F., and Gary H. will invite a representative from Eagle Lake, First Lutheran, and Our Lady of the Lake to our next meeting.   

In addition, to a Q & A, we will ask them to provide us with the following: 

1)      What ended up being really good about what they did.

2)      What would they have done differently if they could do it all over again?

3)      How did they know they were ready for the professionals to come and be a part of the project? 

4)      Are we at that point?

5)      How did they handle the funding of their building projects? 

The meeting was adjourned at 7:50 p.m.  The next BPC meeting will be Thursday, August 12th at 6:30 p.m.   

July 20

Present:  Dave Willey, Chuck Erickson, Richard Hagemeister, Sandi Thorson, Pastor Jim, Dick Gyllstrom, Tanya and Byron Hensch, Stuart Fleischauer, Connie Hanyzewski and Jon Hartman.  Recording Secretary:  Lynn Melchior. 

The meeting began at 5:58 pm. Dave Willey commented that the BPC members have adopted an sense of pragmatism.  This fits well with our congregation.  Dave also discussed the good thinking of multi-use space where functionality of several areas can be met with one room.  As Zion’s space needs are coming together, the BPC can begin moving towards solutions for the space needs.   

Each subgroup then reported their status: 

        EDUCATION:  Tanya H reviewed the Ed subgroups last meeting which focused on multi-use rooms, utilizing existing areas and the possibility of not needed a dedicated 7th and 8th grade room.  This age group may be better suited using different areas of the church as needed by their lesson plans.  Please see BPC ED 7-19-10 minutes for more information. 

The possibility of having weekday daycare at Zion was discussed.  Experiences of other church day cares were expressed; location was discussed (SS rooms) and the fact that this is not necessarily a money maker for Zion but an outreach possibility. Zion’s location may be too remote from people’s work and hospitals to be comfortable for some parents.   

A Nursery was discussed.  Where should this room be located?  Could it be multi-used with Prek/Kdg/Mops?  The Nursery will need to meet all applicable codes (which can be tough) and have speaker/video system installed in order to hear/see the service.  

Adult Education/Family Room was discussed.  This is thought to be a large room that can hold a minimum of 50 people.  It could be used as a fellowship overflow.  However, it was also discussed that if this is also used as a family room for weddings, funerals, etc then perhaps it should be more near the administration and Narthex areas. 

        ADMINISTRATION:  Dick G reviewed their interim report.   Note:  This report basically covers a summary of Sq. Ft. estimates with some specific pertinent comments.  Final report to follow

1.    Pastors Office

-  Space needs     256 Sq. Ft. minimum/current space is 188 Sq. Ft.

-  Office space to include small conference area with small table and 3 – 4 chairs

-  Consideration of dual entry with access to small conference room

-  Other details included in June 29th meeting with Pastor Jim, Pat and Connie 

2.    Intern Pastor Office

-  Space needs     100 Sq. Ft minimum/current space is 65 Sq. Ft. usable

-  Location in close proximity to Pastor’s Office     

3.    Future Pastor Office (time frame not determined)/ Interim storage/usable space

-  Space needs     200 Sq. Ft.

-  Location in close proximity to Pastor’s Office 

4.    Church Office & Administrative

-  Space needs     480 Sq. Ft./current space is 249 Sq. Ft.

-  Separate adjoining area for office equipment and supplies

-  Includes reception area

-  Easy access to small conference room

-  Other details included in June 29th meeting with Pastor Jim, Pat and Connie 

5.    Parish Nurse and Volunteer Coordinator

-  Space needs      144 Sq. Ft.

 6.    Small Conference Room

-  Space needs      320 Sq. Ft.

-  Includes 80 Sq. Ft. of storage space                 

      Current total Sq. Ft.  502

      Proposed total Sq. Ft. 1500 

      Notes:  1. Offices 1,2,3 and 5 require “internal” viewing window.

                  2. During the course of the study the group noted the opportunity

                      and need for additional Fellowship Hall space.

        WORSHIP:   Sandi T. reported that the worship groups main need was an Apse.  This could easily be created by putting an addition on to the existing sanctuary to the North.  No changes would be made to the existing sanctuary walls.  The Apse would allow for music needs, music storage and the sacristy.  It would have an access to the parking lot as well.   

        INFRASTRUCTURE:  Chuck E. reviewed his findings on obtaining and energy audit for Zion.  He reports the energy audit costs which are between $2,500 and $4,500 will be picked up by Lake Region and Great River Energy.  Chuck received permission to get started on the energy audit.  The infrastructure subgroup’s meeting notes are as follows:  

Scope:      

Building Issues Sub-committee is tasked to identify, investigate/analyze, document and recommend an approach to areas within the Zion church’s property, structural & land, that require decisions generic to a new, existing, remodel or add-on structure. 

The sub-committee will state issues as well as identify opportunities that provide cost effective approaches to building, maintaining, energy savings and future needs of the congregation. 

Items of Coverage:

Areas identified to date that require investigation include the following.  This is to be a living document as the project progresses. 

HEATING & COOLING

-         Cost analysis & facility analysis of existing structure over the last 5 years.  Heat vs cooling/other.

-         Perform thermal analysis of existing structure

-         Make recommendations of energy upgrade to lower yearly costs by 25% by 2012

-         Develop plan on cost effective ways to heat & cool

○ Sanctuary

○ Narthex

○ Offices

        ○ Sunday School Rooms

        ○ Kitchen/Fellowship Hall

-         Insulation upgrades needed

-         Suggestion as to enclosed areas with doors vs openness

-         Programmable thermostat/facility usage/peak load

-         Suggesting to architect as to ceiling 8’,  9’, 10’, vault, etc. (room volume)

-         Geothermal investigation and plan 

HOT WATER SYSTEM

    ○ Centralized vs location/demand

    ○ Off peak

    ○ Type of heaters 

WELL

    ○ Size of existing well (capacity)

    ○ Future needs

-   God’s Acres or other

-   Expansion of facility 

SEWER OPTIONS

    ○ Additional location

    ○ Leave as is

    ○ Modify existing system 

RE-SHINGLE

    ○ Upgrade insulation (R-Value)

    ○ Wafer Board concept

    ○ Redesign of ceiling (internal) 

WINDOW SELECTION ON NEW AREAS & REMODEL/EXISTING 

SIDING SELECTION ON NEW AREAS & REMODEL/EXISTING 

OLD DRAWINGS

    ○ Review “old” drawings for pertinent data

    ○ Existing R Value

    ○ Structural designs 

ELECTRICAL COVERAGE

○ Present size

    ○ Increase amperage anticipated     

    ○ Major load change, off peak, etc. 

PARKING LOT MASTER PLAN

○ Where (design plan)

○ When

○ Fill

    ○ Coverage

    ○ Etc. 

SUNDAY SCHOOL ROOM (existing)

    ○ Roof removal & replacement plan

SITE PLAN

    ○ Develop master drawing (scale) of existing structure, set backs, well, sewer, power poles, transformer, parking lot, entrances, etc. 

PRIORITIES:

On going meetings have resulted in prioritizing the list, in that energy cost control is top priority, e.g. heating & cooling and/or associated insulation (or lack of) must be addressed. 

As building plans go forward, new additions must address latest energy savings but existing structure must be looked as an opportunity to bring them up to speed.  As an example, outside wall of the fellowship area (west side) should be upgraded to Hi-R value.  Options may be to go from a 2 x 4 thick wall to a 6” wall with Hi-R such as foam and possible new windows. 

To get a handle on existing structure heat loss, a thermal analysis is suggested for all areas of the buildings.  This is probably going to be a cost item to the congregation unless a cost share is offered. 

Heating and cooling and all the options are being addressed as a priority.  With all the different build phases over the years, what is the right answer for total control of our energy costs?  Is it to go total Geothermal for heating/cooling energy source, keeping some existing systems, modularize new system, etc. 

Priorities are being established to ensure that near term projects must be coordinated so as nothing has to be redone during the new building process. 

PRESENT STATUS:

To date presentations have been made by LREC on Geothermal and opportunities for horizontal boring as to cost benefits along with a lease vs buy option. 

Barry Excavation has discussed present sewer and possible future county/state waste disposal requirements. 

ON GOING DEVELOPMENT:

To implement a priority item of thermal analysis of existing structure, LREC has been contacted.  They have stated an effort will be performed for Zion but anticipated a cost between $2500 to $4500.  However, they have now offered that Great River Energy will pay for half the cost & LREC will pay for the other half.  Therefore, no cost to Zion Lutheran Church.  The energy audit will be performed by a mechanical engineer from Kerkhoven, MN once be can be scheduled.  Chuck Erickson will coordinate the effort.   

The site master plan is ongoing as to existing structure, well, sewer, power pole, etc. 

Parking lot master plan is being developed. 

“Old” drawings are under review. 

The meeting was adjourned at 7:07 pm.  The next BPC meeting will be Thursday, July 29th at 6:30 pm. 

July 19, 2010

Present:  Tanya Hensch, Muriel Foster, Karen Zell, Dave Willey, and Lowell Wilcox.  Recording Secretary:  Lynn Melchior. 

The meeting started at 6 pm.   

The subgroup discussed the advisability of having as many rooms as possible being cross utilized.  For example, could the adult ed room or the SS common room be used also for fellowship expansion and overflow?  Multi-use rooms are good selling points. 

The subgroup also discussed the assets we currently have in courtyards and landscaping – and how to incorporate those in current planning.  The possibility of removing the fireplace (which is non functional) and replacing the space with doors and windows to utilize outside fellowship was discussed.  

To better understand possible expansion space, the group walked around the outside of the church exploring possible areas of expansion for the Education needs.  Dave Willey was able to point out several options. 

The remainder of the meeting was spent discussing room requirements for education.  The rooms discussed were:  Adult Ed, SS Common, PreK/Kdg/Mops, 1st – 2nd grades, 3rd – 4th grades, 5th – 6th grades, 7th and 8th grades, storage/utilities, restrooms, Youth and Library. 

The notes for each room requirement will be updated and emailed to each BPC: Education group member.  

The meeting adjourned at 7:43 pm.

July 8, 2010

Present: Dennis Westlind, Keith Fleischauer, Le Boyer, Dave Willey, Chris Maudal, Chuck Erickson, Richard Hagemeister, Lowell Wilcox, Sandi Thorson, Gary Harrington, Betty Johansen, Karen Frederickson, Pastor Jim, Dick Gyllstrom, Marilyn Wahlgren and Laremie Barry. Recording Secretary: Lynn Melchior.

The meeting began at 6:31 pm. Dave Willey began the meeting talking about the next steps for the BPC. See Handout “Building Committee Interim Report Outline”. Thru the various subgroups, the BPC is looking to consolidate the data in a more concise format; to create a document that is a statement of needs just short of a floor plan. This will help determine the specific building/floor plans needed. Several questions still need to be answered:

  1. What programs and services will Zion offer in the future? How will this affect the proposed building?

  2. What does Zion predict for membership growth?

  3. How do we meet our parking needs – currently and in the future?

Dave suggested that we set aside the idea of a new sanctuary and think thru options with the existing facility and extending the existing facility. For example, if the roof line was extended to the south in the current administration area to the setback line, the added space would be 1,620 sq ft. How could that new space be used and how could the old admin space be used? It is in exploring the reasonable options that meet the major needs that will help in exploring additional options (like new worship space). If we determine that a new sanctuary is needed, then how best to handle the old space will be discussed.

Additional expansion space estimates are: Expand admin and library to the south and 2,304 sq ft is added. Once the education second floor is removed, 320 sq ft is available. Further expansion North and West of the current Sunday School space allows for even more expansion space. NOTE: Removal of the 2nd floor of the Sunday School wing constitutes a 1,800 sq ft space loss that will have to be made up somewhere else.

Secure storage (fire proof) was discussed and assigned to the Admin subgroup. It was also noted, that people need quick access to the admin area, so that must kept in mind when planning the Admin area. Prioritization of needs, common space, user communities, and double door entries were also discussed. The Infrastructure subgroup will focus on how current facilities are working, how they will work with the proposed building and what Zion needs to move toward.

ACTION ITEMS:

  1. A current site plan is needed. Dennis Westlind and Dick Hagemeister will create a drawing that will show current facilities, setbacks, well, septic, etc. A box of drawings in the large Sunday School Room may help with this.

  2. Subgroups need to be more formalized. Lynn will send out a subgroup listing.

  3. A form will be created to help the subgroup formalize their respective needs.

There is a conflict with BPC meeting times for the next two weeks. It was determined that each subgroup will need to meet individually next week to work on their needs forms. The following week, the BPC as a whole will meet on Tuesday July 20th at 6:00 pm.

July 1, 2010

 MAIN MEETING: Present:  Amy Drake, Dennis Westlind, Keith Fleischauer, Le Boyer, Dave Willey, Muriel and Vern Foster, Gary Johnson, Tanya and Byron Hensch, Chuck Erickson, Richard Hagemeister, Lowell Wilcox, Sandi Thorson, Pat Garza, Gary Harrington, Casey Haack, Betty Johansen, Karen Frederickson, Pastor Jim, Intern Pastor Chris, Diane Weeks, Connie Hanyzewski, Dick Gyllstrom and Laremie Barry.  Recording Secretary:  Lynn Melchior. 

The meeting began at 6:25 pm. The first order of business was a presentation by Dan, Energy Services Director at Lake Region Power on Geothermal technology and how it might benefit Zion.  The Geothermal technology can be used for heating and cooling. It uses the renewable energy from the earth to heat and cool.   

Lake Region is offering a new program where they own, install and maintain the closed loop system and a fixed monthly charge is added to your electric bill. (The building owner must still pay for the heat pump and duct work.)  This monthly charge is fixed for 35 years.  It effectively locks in your heating and cooling charges, which are 70% of your energy consumption.  Occasionally a secondary heating source may be needed. The remaining 30% of the energy charges is lights, appliances, etc.  This is primarily a residential process – commercial buildings need customized installations and charges.  The closed loop system can be purchased at a depreciated price.  Current prices for a horizontal bore are $1,700 and $1,800 to $2,100 vertical.  Well locations are depicted in the easement with GPS locations. 

Lake Region utilizes horizontal drilling at a depth of 15 ft for 200 – 250 ft in length.  The soil type, loads needed and distance between pipes must be known for geothermal sizing.  Vertical drilling can also be used in Geothermal technology but then a well driller must be involved as anything deeper than 25 feet requires a well drilling permit.  The pipes are filled with methanol.  Backfill is used to maximize energy conduction.  Easements may need to be recorded and setbacks observed on smaller lots.  Test bores may also be needed for larger projects.  An existing structure should have an energy audit.   

A video showed horizontal drilling and talked about the merits of geothermal.  Dan also provided a handout that covers the new geothermal program at Lake Region. 

The second order of business was to create a new sub group of the BPC.  It will focus on worship and fellowship.  Current members are Sandi, Amy, Pastor Jim and hopefully, Chris Maudal.   

Two additional handouts were also provided:  Betty Johansen of the library committee passed out the long range planning request for the Zion Library.  Dave Willey passed out ELCA suggestions for church sizing.   

INFRASTRUCTURE SUB-GROUP: 

Immediately after LREC presentation, the infrastructure sub-group discussed “sewer” with Laramie Barry.  Attendees were Chuck Erickson, Keith Fleischauer, Dick Hagemeister, Dennis Westlind, Stuart Fleischauer, Pastor Jim, Le Boyer and Gary Johnson & Lowell Wilcox.  Recording Secretary: Dennis Westlind. 

Items discussed:

   ●  Present drain field at north of kitchen is approximately 3 feet by 25 feet with a “small” tank.

   ●  Appears that kitchen and sanctuary bathrooms are “Y’d” towards small tank.

   ●  Present field has not been disturbed except for adding cleanout Y and

       additional pipe for future heat tape (or steam).  Work done because of “deepfreeze”.

   ●  We probably don’t need to update existing field but church expansion may dictate another field or change existing field (it is building design dependent).  May need lift pump.

   ●  We are presently at approximately 600 members.

   ●  25 to 30 Sunday School attendees

   ●  Dishwasher will require 50% bigger tank on new system (County/State rule).

   ●  As a “swag” our new plan may require a tank(s) and leach field similar to a 4 bedroom house (may go to that of 5 bedroom house equivalent).

 

ADMINISTRATION:

The administration sub-Group met on June 29th.  The following is the minutes from that meeting.  

Zion Bldg/Planning Committee

Meeting with Pastor Jim, Pat G. and Connie June 29, 2010

From: Dick Gyllstrom and Diane Weeks

Subj.: Pastor/Office Administrative Offices 

The purpose of the meeting was to explore office requirements and needs.  The primary goal was to discuss the variety of musts, needs and wants typically found in the Pastor/Office Staff office complex. 

Pastors Office

-         Space for small counseling area, 3 to 4 chairs with small table for personal counseling (family, marriage, etc.)

-         Possible dual entry

-         Have Senior Pastor/Assoc. Pastor/Intern office proximity

-         Easy access to separate staff/general purpose meeting room

-         Personal Library Space (basically bookshelves)

-         Closed Cabinets (Lockable)

-         Lockable AV equipment storage unless located in general office area

Note:  Some measurements were taken of Pastor’s existing office to determine if present size would be adequate.  Determined that the 256 Sq Ft noted in the June 24th group meetng notes would be adequate and needed. Other area sizes noted in those notes will likely need to be further evaluarted as we go.

 

Church Office and Associated Space 

-         Recommend open area with controlled access/ counter between office space and visitors.

-         Need space for coats/personal items

-         Upgrade phone system/more flexibility

-         Lockable space for Audio/Visual

-         Copy Area/need functional, controlled space

-         Security Vault

-         Need detailed review of PC use and needs

-         Use close proximity conference/meeting room for organizing mass mailings

Note:  There were other office/productivity/work related ideas that should be considered that do not necessarily affect square footage requirements. 

Further detailed discussion will be needed as space layouts and other options are considered. 

The BPC will meet weekly on Thursday evenings at 6:30 pm.  The next meeting is July 8th.   Thoughts and comments can be emailed to Dave Willey in between meetings.*

June 24, 2010 

Present:  Stuart Fleischauer, Amy Drake, Dennis Westlind, Keith Fleischauer, Le Boyer, Dave Willey, Muriel and Vern Foster, Gary Johnson, Tanya Hensch, Chuck Erickson, Susan Thompson, Richard Hagemeister, Lowell Wilcox, Sandi Thorson, Pat Garza, Gary Harrington. 

This BPC meeting was divided into 3 basic areas to investigate, start qualifying and documenting requirements.  The areas discussed were administration, education and infrastructure.  The three groups met separately for 45 minutes to define these needs. 

ADMINISTRATION: 

Participants were:  Sandi Thorson, Pastor Jim, Vern Foster, Pat Garza, Susan Thompson, Gary Johnson, and Gary Harrington, who facilitated.  Pat Garza was the Administration meeting recorder. 

Administration square footage proposed.

Pastor’s office—256 sq ft

Intern office—86 sq ft

Secretary—360 sq ft

Parish nurse—190 sq ft

Future associate Pastor—200 sq ft

Conference/meeting room—480 sq ft 

bulletThe need for 2 phone lines and an intercom system.
bullet Pastor needs more storage.
bulletA buffer at the entrance of the administrative area is important.
bulletA sitting area for Pastor so the desk is not a barrier when counseling.
bulletA lockable area for audio/visual storage.
bulletSpace in the main office for confidential and financial work.  Perhaps with a 2-way mirror.
bulletVault for permanent records.
bulletThe parish nurse office could be co-used with a volunteer coordinator.
bulletThe Intern Pastor office should be located across from or next to Pastor’s office.

The July 1 meeting will focus on square footage needs for each of the above areas.

EDUCATION: 

Participants were:  Amy Drake, Muriel Foster, Lowell Wilcox, & Tanya Hensch.  Tanya Hensch was the Education meeting recorder.

****STORM SHELTER ROOM was felt to be a priority. Could a basement be put under a small portion of the new addition somewhere?

(Current upstairs area is 32' X 35' for classroom end; this area includes a 4' wide hallway the entire length. The big room is 16' X 32'.  Classrooms are too small; access to bathrooms has too narrow of a hallway. Very little storage.)

**Ideas for NEW SUNDAY SCHOOL area:
1.  5 classrooms needed (Pre & Kdg.,  first & second, third & fourth, fifth & sixth, and seventh & eighth) Size of these rooms to be discussed at next meeting, but three of these five rooms need to be larger, with two being smaller in size.
2.  Pre & Kdg. room needs to be one of the larger rooms, and can also accommodate MOPS group.  Should have its own storage area, activity sink, and separate bathroom with lower-sized  fixtures and a changing table. It needs to have an area of tables and chairs for activities, but also a large open "floor" area to allow for "circle time".  This room needs to have walls that are well-insulated to deter noise.
3.  Smaller "central" storage area that is easy access to all classrooms: would contain lots of shelving, small copier machine, TV on a cart, extra table storage, extra stackable chairs, etc..
4. White boards needed in each classroom and access to internet.
5. Easy access to an outdoor playground area that is fenced in.

**Ideas for ADULT ROOM:
1.  Needs to be large enough to accommodate 40 - 50 people.
2.  Needs to be carpeted.
3.  Should have its own counter area which would include a sink and Microwave.
4.  Needs to have smaller tables and chairs, but also comfortable couches and chairs.
5.  Should also have a whiteboard, projector system,  and TV.
6.  Should have a speaker system, but be able to control the volume.

**Ideas for NEW LIBRARY:
1.  Existing library is approximately 13' X 18'; new Library should be tripled in size, around 700 square feet.
2.  Needs to have more tables and chairs.
3. Computerized card catalog.
4. History Interpretation Wall or area within the room.
5. Two or three computers available to be used by members, but would need somehow to lock up this counter area somehow.
6.  Much more shelving needed.
??? Is this a room that needs to be locked up at the end of the day???
 

INFRASTRUCTURE:
 

Participants included Keith Fleischauer, Stuart Fleischauer, Le Boyer, Chuck Erickson, Vern Foster, Dick Hagemeister, Lowell Wilcox & Dennis Westlind.  Dave Willey facilitated.  Recorder at Infrastructure meeting – Dennis Westlind 

Certain areas need to be addressed.  The intent is to document where we are now and what needs to be done before the decision making process is implemented.  These areas require the team to become smarter in each since approach will apply in one way or the other no matter what our final configuration looks like. 

General areas to be addressed are:

-         Sewer

-         Water

-         Electric

-         Heat & Air

-         Solar (wind energy supplement)

-         Property Entrance Restrictions 

Areas to be explored hopefully during next meeting (July 1) are:

-         Laremie Barry to be contacted by Chuck as well as Lowell as to follow-up to existing drain field, tanks and what is coming down the pipe for new requirements by State (or County) and what do we need to be ready for, e.g. changes because of remodeling and addition of plumbing fixtures.  Can we have more than 1 tank/drain field if location dictates?

-         Lake Region Electric ideas on geo-thermal heating & air.  They are exploring horizontal drilling for thermal loops.  Chuck to request LREC to give us update.

-         LREC also provides thermal inspection of facilities to identify hot spots.  Chuck to explore.

Other areas to be addressed are:

                -         How do we increase “R” when we re-shingle “old sanctuary” or other roofs?

-         Should we consider some form of “storm shelter” inclusion in our plan?

-         As an after thought, suggest a few members of the committee develop a plot plan (scale drawing) of existing buildings, roads, parking, sewer tank/leach field, country road r/w, power pole/transformer/pedestal, etc.

 Notes of Interest:

1)    Present fireplace is non-functional.  Should it be removed if not conducive to expansion?

2)    It appears that Sunday School roof & upper story could be removed after other expansion is done.  Minor repairs would allow another few months (years) of service.

3)    Existing kitchen is very usable, however, more eating area could be pursued.

4)    Present electric service includes 2-200 amp service panels.

5)    Electric management and heating/air is one of the major cost drivers in church budget. 

The BPC will meet weekly on Thursday evenings at 6:30 pm.  The next meeting is July 1st.   Thoughts and comments can be emailed to Dave Willey in between meetings.

June 17, 2010 

Present:  Stuart Fleischauer, Amy Drake, Dennis Westlind, Keith Fleischauer, Le Boyer, Dave Willey, Muriel and Vern Foster, Gary Johnson, Tanya Hensch, Chuck Erickson, Susan Thompson, Richard Hagemeister, Lowell Wilcox, Sandi Thorson, Pat Garza, Gary Harrington. 

This BPC meeting was divided into 3 basic areas to investigate, start qualifying and documenting requirements.  The areas discussed were administration, education and infrastructure.  The three groups met separately for 45 minutes to define these needs. 

ADMINISTRATION: 

Participants were:  Sandi Thorson, Pastor Jim, Vern Foster, Pat Garza, Susan Thompson, Gary Johnson, and Gary Harrington, who facilitated.  Pat Garza was the Administration meeting recorder. 

Administration square footage proposed.

Pastor’s office—256 sq ft

Intern office—86 sq ft

Secretary—360 sq ft

Parish nurse—190 sq ft

Future associate Pastor—200 sq ft

Conference/meeting room—480 sq ft 

bulletThe need for 2 phone lines and an intercom system.
bulletPastor needs more storage.
bulletA buffer at the entrance of the administrative area is important.
bulletA sitting area for Pastor so the desk is not a barrier when counseling.
bulletA lockable area for audio/visual storage.
bulletSpace in the main office for confidential and financial work.  Perhaps with a 2-way mirror.
bulletVault for permanent records.
bulletThe parish nurse office could be co-used with a volunteer coordinator.
bulletThe Intern Pastor office should be located across from or next to Pastor’s office.

The July 1 meeting will focus on square footage needs for each of the above areas.

EDUCATION: 

Participants were:  Amy Drake, Muriel Foster, Lowell Wilcox, & Tanya Hensch.  Tanya Hensch was the Education meeting recorder.

****STORM SHELTER ROOM was felt to be a priority. Could a basement be put under a small portion of the new addition somewhere?

(Current upstairs area is 32' X 35' for classroom end; this area includes a 4' wide hallway the entire length. The big room is 16' X 32'.  Classrooms are too small; access to bathrooms has too narrow of a hallway. Very little storage.)

**Ideas for NEW SUNDAY SCHOOL area:
1.  5 classrooms needed (Pre & Kdg.,  first & second, third & fourth, fifth & sixth, and seventh & eighth) Size of these rooms to be discussed at next meeting, but three of these five rooms need to be larger, with two being smaller in size.
2.  Pre & Kdg. room needs to be one of the larger rooms, and can also accommodate MOPS group.  Should have its own storage area, activity sink, and separate bathroom with lower-sized  fixtures and a changing table. It needs to have an area of tables and chairs for activities, but also a large open "floor" area to allow for "circle time".  This room needs to have walls that are well-insulated to deter noise.
3.  Smaller "central" storage area that is easy access to all classrooms: would contain lots of shelving, small copier machine, TV on a cart, extra table storage, extra stackable chairs, etc..
4. White boards needed in each classroom and access to internet.
5. Easy access to an outdoor playground area that is fenced in.

**Ideas for ADULT ROOM:
1.  Needs to be large enough to accommodate 40 - 50 people.
2.  Needs to be carpeted.
3.  Should have its own counter area which would include a sink and Microwave.
4.  Needs to have smaller tables and chairs, but also comfortable couches and chairs.
5.  Should also have a whiteboard, projector system,  and TV.
6.  Should have a speaker system, but be able to control the volume.

**Ideas for NEW LIBRARY:
1.  Existing library is approximately 13' X 18'; new Library should be tripled in size, around 700 square feet.
2.  Needs to have more tables and chairs.
3. Computerized card catalog.
4. History Interpretation Wall or area within the room.
5. Two or three computers available to be used by members, but would need somehow to lock up this counter area somehow.
6.  Much more shelving needed.
??? Is this a room that needs to be locked up at the end of the day???

 

INFRASTRUCTURE:

Participants included Keith Fleischauer, Stuart Fleischauer, Le Boyer, Chuck Erickson, Vern Foster, Dick Hagemeister, Lowell Wilcox & Dennis Westlind.  Dave Willey facilitated.  Recorder at Infrastructure meeting – Dennis Westlind 

Certain areas need to be addressed.  The intent is to document where we are now and what needs to be done before the decision making process is implemented.  These areas require the team to become smarter in each since approach will apply in one way or the other no matter what our final configuration looks like. 

General areas to be addressed are:

-         Sewer

-         Water

-         Electric

-         Heat & Air

-         Solar (wind energy supplement)

-         Property Entrance Restrictions 

Areas to be explored hopefully during next meeting (July 1) are:

-         Laremie Barry to be contacted by Chuck as well as Lowell as to follow-up to existing drain field, tanks and what is coming down the pipe for new requirements by State (or County) and what do we need to be ready for, e.g. changes because of remodeling and addition of plumbing fixtures.  Can we have more than 1 tank/drain field if location dictates?

-         Lake Region Electric ideas on geo-thermal heating & air.  They are exploring horizontal drilling for thermal loops.  Chuck to request LREC to give us update.

-         LREC also provides thermal inspection of facilities to identify hot spots.  Chuck to explore. 

Other areas to be addressed are:

-         How do we increase “R” when we re-shingle “old sanctuary” or other roofs?

-         Should we consider some form of “storm shelter” inclusion in our plan?

-         As an after thought, suggest a few members of the committee develop a plot plan (scale drawing) of existing buildings, roads, parking, sewer tank/leach field, country road r/w, power pole/transformer/pedestal, etc.

Notes of Interest:

1)      Present fireplace is non-functional.  Should it be removed if not conducive to expansion?

2)      It appears that Sunday School roof & upper story could be removed after other expansion is done.   Minor repairs would allow another few months (years) of service.

3)      Existing kitchen is very usable, however, more eating area could be pursued.

4)      Present electric service includes 2-200 amp service panels.

5)      Electric management and heating/air is one of the major cost drivers in church budget.

 The BPC will meet weekly on Thursday evenings at 6:30 pm.  The next meeting is July 1st.   Thoughts and comments can be emailed to Dave Willey in between meetings.

June 17, 2010

Present:  Stuart Fleischauer, Amy Drake, Dennis Westlind, Keith Fleischauer, Le Boyer, Dave Willey, Muriel and Vern Foster, Diane Weeks, Karen Frederick, Dick Gyllstrom, Gary Johnson, Bryon and Tanya Hensch, Chuck Erickson, Susan Thompson (observer), Richard Hagemeister, Casey Haack, Chris Maudal, Karen Zell, Intern Pastor Chris Zuraff, Jim Olson.  Recording secretary:  Lynn Melchior  

Summaries of past Space Task Force were posted on the walls for review. 

BOF summary, Opening Devotions and BOF (Philippians 2:1 – 11) were led by Intern Pastor Chris.

Meeting began at 6:30 with Jim Olson summarizing the function of the Building Planning Committee (BPC).  He noted that space needs have long been talked about – the numbers of activities at Zion have increased over the years.  In fact, the current BPC meeting has a space conflict with the contemporary music team as the sanctuary was double booked.   

Jim defined the purpose of the BPC as moving forward with the space issue; to get something done.  Dave Willey will be the Chair.  The committee is a large one that is congregation based.  All congregation members have an open invitation to attend any and all BPC meetings.  Meeting minutes will be sent out via email.  For those without email, a hard copy can be picked up at the office. 

~~A 10 minute break for cookies and lemonade~~ 

The meeting reconvened in the Sunday School Music Room.  Dave Willey led the final portion of the meeting. Dave listed the proposed space priorities of the BPC as:

        Education

        Administration

        Worship

        Fellowship

Dave plans on organizing the BPC into smaller groups (i.e. education, administration, infrastructure, etc). People with expertise in those areas will lead the smaller groups. Congregation members outside of the BPC will be invited to the smaller groups as well.   

Dave reviewed a handout with the proposed order of tasks to be carried out by the BPC.  A question was raised as to whether future space needs were considered by the previous task force.  Dave believed they did to some extent. Jim Thomas had done some demographic summaries and projection.  It was noted that these may need to be updated however; we need not rehash all the work done by the earlier Space Task Force. 

A question was raised as to how the building itself encourage growth. The ELCA believes that limiting factors of a church are twofold:  parking and sanctuary space.  It is believed that we have ample sanctuary space and the parking lot is being worked on.  It was also noted that supporting Mothers builds strong congregations.

Dick Hagemeister reviewed two possible plans for the future space of Zion.  He noted that there are several ways of doing a large project such as this:  Phased and All At Once. He noted that the Phase approach could cost as much as 4% more. Discussion followed as to the pros/cons of the possible plans and keeping the 2nd floor (1800 sq ft) for other uses.  It was noted that nothing has been decided yet. 

Many wants and needs were discussed:  

·        Technology to be included in the Education space

·        Determination of the function and flow of each space

·        Both private and social space for work to be done

·        Open space for various activities (i.e. MOPS)

·        Ample space for future growth (i.e. Associate Pastor)

·        Dividable rooms (quality dividers needed)

·        Bathrooms in the Sunday School Areas

·        Handicap accessibility in all areas of Zion

·        A separate bathroom in the nursery area

·        Infrastructure review

·        Wise use of old/current building space

·        Best use of our current property (including God’s Acres)

·        Accurate budget and detailed plans

·        Maintaining the beautiful sightlines of the current building

·        Youth Room (Youth = 6th grade to college)

·        Separate copier space from the office (due to noise)

·        Technology infrastructure

·        Family/Multipurpose Room

·        Children taking ownership in the BPC projects

·        A better cross section of the congregation on the BPC

·        Inviting and easy access to various areas of the church

A focus and understanding of the known and predicted functions of the church will be key to the success of the BPC.

The BPC will meet weekly on Thursday evenings at 6:30 p.m.  The next meeting is June 24th.   Thoughts and comments can be emailed to Dave Willey in between meetings.

The meeting was adjourned at 8:12 p.m.

 

Home ] Up ] Calendar ] Announcements ] Foundation ] Get Involved ] Learn With Us ] Library ] New Members ] Photo Gallery ] Sermon ] Visit Us ] Worship With Us ] Youth ] Zion History ] Zion Staff ]

Contact Connie with questions or comments about this web site.
Copyright © 2006 Zion Lutheran Church of Amor
Last modified: 05/01/10
 Hit Counter